Call Us Today: +1 866 205 2414
By Varun Persaud
Shutdowns and turnarounds are among the most carefully planned events in mining and industrial operations. Every day offline translates to lost revenue, delayed production, and ripple effects throughout the supply chain. Yet despite the importance placed on preparation, shutdown projects continue to overrun both budgets and schedules at an alarming rate.
A global benchmarking study by Independent Project Analysis (IPA) found that 65% of shutdowns experience budget overruns of more than 15%, and nearly half miss their scheduled completion date. The root cause? A fundamental disconnect between what is scoped and what is planned.
This disconnect isn’t just a planning oversight—it’s a structural misalignment between two competing forces. On one side, operations and technical teams define the scope, which outlines what must be done. On the other side, project teams build a schedule around how and when it will be done. When those two elements are misaligned—or worse, developed in isolation—shutdowns fail before execution even begins.
The scope defines the boundaries of the work, including which systems will be affected, which assets will be replaced, which inspections will be conducted, and what upgrades are scheduled. It is the technical expression of why the shutdown is happening.
But in many organizations, the scope development process is informal or reactive. Teams rely on institutional memory, legacy spreadsheets, or tribal knowledge to define work packages. As a result, critical tasks are missed while low-priority items sneak in. More dangerously, scope is often added well into the pre-execution phase, after procurement, workforce planning, and scheduling have already been completed.
In one 2023 turnaround at a copper mine in Chile, over 20 new work packages were added after the schedule had been locked. This required tearing down and rebuilding the entire project timeline, leading to procurement delays, field congestion, and over $2.8 million in change order penalties.
Without a frozen, risk-assessed scope, the schedule is pure fiction.
While scope defines what to do, the schedule defines how to do it. It sequences activities, allocates resources, and establishes a critical path. When done well, it enables efficient field execution, coordinated handoffs, and predictable performance.
But too often, the schedule is built on flawed assumptions:
These assumptions collapse quickly in the field. A 2022 mining shutdown in Ontario showed that only 60% of tasks on the original Gantt chart were executed in the planned sequence. The rest were either delayed, resequenced, or deferred due to unforeseen conflicts, many of which stemmed from scope additions made too late in the process.
In another example, a large energy producer developed a shutdown schedule based on an 85% wrench time per shift. In reality, congested work zones, delayed access permits, and contractor confusion resulted in productivity levels of under 50% during the first five days. By the end of the project, total costs had ballooned by 38%.
A schedule that doesn’t reflect the actual scope and real-world constraints is simply a guess.
The root problem lies in how many organizations treat scope and scheduling as parallel rather than integrated processes. In theory, planners take a finalized scope and build a schedule. In practice, scopes continue to evolve while schedules are already being finalized. This leads to misalignment in work durations, logic links, resource allocation, and material needs.
This gap is widened when:
The result? Schedules are based on incomplete or inaccurate information and become increasingly disconnected from the real workload.
A North American smelter planned a $40 million turnaround with a 28-day shutdown window. The scope was finalized three months before the outage, but leadership allowed for minor additions until the shutdown commenced. These “quick adds” came from maintenance leads, plant managers, and regulatory reviews.
In total, 34 additional work items were added after the freeze. While each was small in cost, collectively they required 14% more labor and 10% more equipment hours. The schedule, however, was never updated to reflect these changes. When execution began, crews were double-booked, materials were late, and contractors weren’t ready for the extra work. The project ultimately ran nine days over and exceeded budget by 22%.
A post-mortem revealed that, despite the execution team flagging the schedule as unrealistic, senior leadership insisted it was “locked.” The planning gap cost the organization millions in idle time, liquidated damages, and lost production.
To close the gap between scope and schedule, leading organizations implement an integrated shutdown planning model. This model emphasizes cross-functional input, structured freeze points, and dynamic alignment between what is planned and what is resourced.
Here are four proven strategies:
At TMG, we help organizations avoid the hidden cost traps of poor shutdown planning. Our methodology integrates scope and schedule development from the outset, ensuring that what is planned is executed and that any additions are adequately resourced and, where required, resequenced.
We work directly with technical leads, schedulers, procurement teams, and contractors to develop executable plans grounded in real-world constraints, rather than optimistic assumptions. We enforce governance models that strike a balance between flexibility and control, ensuring that late-breaking needs don’t derail your entire project.
The result? Shutdowns that stay on track, avoid scope-schedule friction, and deliver predictable outcomes.
TMG specializes in executive and operational consulting for the Mining, Energy, and Infrastructure sectors. We provide tailored oversight and strategic guidance across all project stages, ensuring optimal outcomes from conception to execution.
TMG committed to diversity and inclusion, based on the undisputed fact, that a fully inclusive environment, fosters a unique perspectives that can solve challenging problems and creates value, within the company, for our clients, the communities of which we work, and the world at large.
TMG’s corporate vision and values, are to honour the rights and cultures of all people and respectfully approach all business, with fair dealings and establishing and maintain a mutually respectful relationship.
TMG acknowledges that our offices are located on traditional lands of divers First Nations and Indigenous peoples. Guided by the Constitution of both Canada & the USA, the United Nations Declaration on the Rights of Indigenous Peoples (UNDRIP) and the recommendations of all Truth and Reconciliation Commission as a framework, we are committed to taking ongoing positive and concrete steps towards reconciliation.